schema:hasPartdcm-retention-schedule C1: KYC documents kept 5 years with no trigger
schema:hasPartdcm-retention-schedule C1: the KYC trigger named as the end of the relationship
schema:hasPartdcm-retention-schedule C1: loan agreements from signing where the extract says contract end
schema:identifierC1
schema:position1
schema:textTriggers, 1 each. (a) RR-001 KYC files '5 years' has no trigger: it cannot be executed. (b) The trigger is named as the extract sets it - the end of the business relationship (LB-001) - and sourced to a recorded date (CRM party.relationship_end_date), not account opening. (c) RR-002 loan agreements run '10 years from signing' where LB-004 says from contract end: trigger changed to contract end (AS-005 loan.end_date). en

Used by

has questionBank retention schedule - from which event, and where is that date? (retention schedule anomaly skills)
schema:isPartOfdcm-retention-schedule C1: KYC documents kept 5 years with no trigger
schema:isPartOfdcm-retention-schedule C1: the KYC trigger named as the end of the relationship
schema:isPartOfdcm-retention-schedule C1: loan agreements from signing where the extract says contract end